Soeteck Prefabricated Container Data Center in Qatar

Sep 16, 2025

Project Background

Against the backdrop of the global digitalization wave—where data has emerged as a core strategic asset—GRD Company has established a deep cooperative partnership with the Qatari government for a key data center project. For this initiative, the client specifically selected Shuayi Technology to develop and construct an innovative 40-foot standard containerized data center for its Qatari branch.

 

Breaking free from the constraints of traditional fixed data center designs, this project is tailored to deliver a mobile data hub for the Qatari branch. The data center is integrated within a rugged 40-foot container and fortified by cutting-edge security technologies, forming an impenetrable defense for both stored data and real-time processing tasks. This ensures ultra-stable operations even amid the dynamic and ever-evolving digital landscape, marking a pivotal milestone in GRD Company’s journey toward full-scale digital transformation.

Technical Specifications of the 40-Foot Container Data Center

The 40-foot containerized data center is fully outfitted with critical infrastructure to guarantee reliability, efficiency, and security, with key specifications as follows:

 

Category Details
Core Equipment - UPS system (including battery cabinet)
- Precision air conditioning
- Comprehensive security monitoring system
Server Cabinets - 10 units total, each with dimensions 600mm × 1100mm × 2000mm
- Single-cabinet load capacity: 6.3 kW
- Total power capacity: 63 kW
Power Continuity - 2 sets of 90 kVA modular UPS systems
- Designed battery backup time: 10 minutes
Cooling System - 4 units of 25 kW in-row air-cooled precision air conditioners
- Ensures efficient thermal management for all equipment
Monitoring & Redundancy - Full DCIM (Data Center Infrastructure Management) system (covers power and cooling components)
- N+1 redundancy configuration for enhanced operational reliability
Power Supply 415V, 3-phase, 50Hz standard power input

Project Challenges & Tailored SolutionsKey Challenges

The container data center is deployed in an environment with extreme conditions:

 

  • Ambient temperature at the site reaches up to 50 °C;
  • Frequent strong sandstorms occur;
  • These conditions lead to two critical risks: equipment overheating and dust clogging, which significantly increase operational instability.

3.2 One-Stop Solutions

To address the above challenges, Shuayi Technology provided a comprehensive, integrated solution with three core measures:

 

  1. High-temperature dedicated air conditioner: Capable of delivering full-load cooling performance even at 50 °C. It has passed long-duration extreme-condition tests, with zero temperature drift during operation.
  2. IP5X high-efficiency filtration system: Effectively intercepts sand and dust particles, extending filter service life by 300% and reducing maintenance intervals by 50%.
  3. Full-chain high-temperature resistant components: All key components (including cables, connectors, and fan motors) are rated for 85 °C operation, lowering the equipment aging rate by 70%.

 

Through the synergy of these three measures, the container data center achieves 24/7 continuous and stable operation even under 50 °C high-temperature and sandstorm conditions.

High-Efficiency Delivery Solution for Urgent Customized Projects

The project faced dual pressures: a compressed delivery timeline and strict technical customization requirements. To meet these demands, Shuayi Technology adopted a "freeze-track-green-channel" three-step method to achieve ultra-short lead-time performance:

 

  1. 24-hour technical freeze: The sales, R&D, and supply chain teams collaborate to conduct a joint review of the BOM (Bill of Materials) and design drawings, locking in all details in one go to eliminate any subseq
  2. Daily progress dashboard: Critical-path tasks are assigned to specific owners, with daily progress reviews. If any task is delayed by more than 8 hours, an immediate alert is triggered to resolve issues promptly.
  3. Supply-chain green channel:
    • Safety stock is maintained for core components to avoid supply gaps;
    • Suppliers of custom components are stationed on-site to streamline communication and production;
    • Logistics rely on dedicated direct trucks to ensure timely delivery of materials and finished products.